ABB is now renovating this transformer and is conducting a renewed trouble shooting of the control systems. This work is expected to last for three weeks.

The net production and delivery loss is estimated to total around 70,000 tonnes, which will impact the fourth quarter of 2016 and the first quarter of 2017, with most of the loss impacting the first quarter. It was earlier estimated that the net production and delivery loss would total around 40,000 tonnes.  

“Very regrettably, the prolonged outage implies further impact on customer deliveries. We will continue to take advantage of SSAB’s flexible production system and where possible reallocate volumes to other production sites,” said Per-Olof Stark, head of SSAB Special Steels.

“It is a top priority for ABB to find a solution together with SSAB. ABB has mobilized all expert resources needed to find a fast and reliable solution,” said Johan Söderström, Managing Director, ABB Sweden. 

For further information, please contact:
Per Hillström, Head of Investor Relations, [email protected], phone: +46 70 295 2912

SSAB AB is obliged to make this information public pursuant to the EU Market Abuse Regulation. The information was submitted for publication, through the agency of the contact person set out above, on January 9, 2017 at 7.15pm CET.